Site description
Treated volume44,975 m³of contaminated soil (80,955 t)
Thermal technologyIn-Situ Thermal Treatment
Main contaminantNSO heterocycles, TPH, PAH, BTEX, TCE/PCE
Site challengesFormer steel and coking plant; full-scale remediation completed in less than one year
Project timeline2018

Solution
- Treatment methodIn-situ thermal treatment with Smart Burners™
- Treatment programPilot of 100 m² (900 m³), then full scale over 32,900 m²
- Contaminated vapour managementRe-Burn
- Process controlContinuous soil temperature monitoring, target temperature 270°C

Results
44,975 m³treated soil volume
< 12 monthsfull-scale treatment, March to December 2018
Site redeveloped as a public park for the 2022 Winter Olympics