Large-Scale ISTD Validation Project at Haemers Technologies Headquarters

Haemers Technologies carried out a full-scale In-Situ Thermal Desorption (ISTD) project at its Brussels headquarters to remediate historical motor oil contamination. The project demonstrated the effectiveness of the technology in treating both contaminated soil and groundwater while preventing further migration into the aquifer.

Site description

Treated volume420 m³of contaminated soil (756 t)
Thermal technologyIn-Situ Thermal Treatment
Main contaminantTPH (C10–C40) in soil and groundwater
Site challengesHistoric motor oil leak beneath the Haemers Technologies headquarters; soil and groundwater treated together
Project timelineMarch 2020 – March 2021
Project site

Solution

  • Treatment methodIn-situ thermal treatment with Re-Burn
  • Treatment program2 batches of 45 burners (propane, natural gas and diesel), target temperature 250°C
  • Contaminated vapour managementRe-Burn; emissions controlled with gas analysers
  • Process control21 temperature probe wells (1, 3.5 and 4.5 m) and 8 pressure wells
Treatment on site

Results

TPH < 300 mg/kg in soil and < 300 µg/L in groundwater
46 + 55 daysheating time (batch 1 + batch 2)
Cross-contamination to the water table stopped
Site during or after treatment

Reference sheet

Technical summary of this project, sent on request.