Large-Scale LNAPL Recovery at the Feyzin Petrochemical Site, France

Haemers implemented a long-term LNAPL recovery system to remediate historical hydrocarbon contamination at a petrochemical facility in Feyzin. The installation was specifically designed to accommodate significant groundwater fluctuations, resulting in the recovery of more than 93 m³ of free-phase hydrocarbons.

Site description

Recovered product> 93 m³of pure product
TechnologyLNAPL skimming
Main contaminantHydrocarbons, BTEX, aromatic and aliphatic compounds
Site challengesAquifer at 12 m with fast 2.5 m variations induced by a nearby river
Project timeline2010–2019
Project site

Solution

  • Treatment methodLong-term LNAPL recovery in a petrochemical unit
  • Treatment program2 DS 500-6D ATEX pumping units and 8 SKIM 4-250 skimmers
  • StorageEach pumping unit connected to a 5,000 L ST 5000 storage unit
  • Process controlOperation controlled by the groundwater level; skimmers follow 2.5 m variations
Treatment on site

Results

> 93 m³pure product recovered over about four years
Continuous operation despite groundwater variations of 2.5 m
Free phase from a few centimetres to several tens of centimetres addressed over a large surface
Site during or after treatment

Reference sheet

Technical summary of this project, sent on request.