Site description
Treated volume12,000 m³of contaminated soil
Thermal technologyEx-Situ Treatment (Applied Onsite)
Main contaminantHydrocarbons (C5–C40), BTEX, PAH, PCE/TCE, residual explosive compounds
Site challengesTreatment of hydrocarbons and residual explosive compounds, maintaining compliant emissions throughout a 9-month period
Project timeline2019

Solution
- Treatment methodMultiple ESTT treatment piles
- Treatment programTwo piles treated simultaneously, a third in mobilization/demobilization, 75 heating tubes
- Contaminated vapour managementEmission standards respected throughout the treatment
- Process controlTarget temperature 150–200°C, 39–52 days per batch

Results
Successfully remediated 12,000 m³
Treatment time: reduced from 53 to 39 days
Treatment batches were validated and accepted by the client

Reference sheet
Technical summary of this project, sent on request.