Site description
Treated volume10,000 m³of contaminated soil
Thermal technologyEx-Situ Treatment (Applied Onsite)
Main contaminantPAH, hydrocarbons (C10–C40), TCE/PCE
Site challengesSoils excavated from several zones along an urban canal
Project timeline2019 – 2021

Solution
- Treatment methodOn-site thermal remediation using Smart Burners fuelled with natural gas
- Treatment program7 batches of approximately 2,700 tonnes each
- Contaminated vapour managementRe-Burn treatment (Vapour Treatment with granulated activated carbon from the seventh batch)
- Process control15 temperature probe wells, 5 pressure wells and a gas analyser

Results
97%average burner operating rate
43–56 daysheating time per batch (batches 2 to 7)
Reference project for heating control and energy consumption