Site description
Treated volume40 m³of contaminated soil (64 t)
Thermal technologyIn-Situ Thermal Treatment
Main contaminantHydrocarbons (C8–C45)
Site challengesCellar of an occupied house and the adjacent garden; contamination between 2 and 6 m
Project timeline2022

Solution
- Treatment method6 natural gas Smart Burners with Re-Burn: 2 in the cellar, 4 in the garden
- Treatment programTarget 220°C at the cold point, 60 days of heating
- Contaminated vapour managementRe-Burn
- Process control4 temperature probe wells (4 and 6 m), 1 pressure well, gas analyses

Results
40 m³treated soil volume
Targets of the engineering office reached down to 6 m (520 mg/kg heavy, 20 mg/kg light hydrocarbons)
60 daysheating time