Site description
Treated volume3,500 m³of contaminated soil
Thermal technologyEx-Situ Treatment (Applied Onsite)
Main contaminantHydrocarbons, BTEX, PAH
Site challengesFormer gas plant in an urban area; C10–C40 up to 33,000 mg/kg, PAH up to 12,000 mg/kg
Project timeline2019–2021

Solution
- Treatment method75 gas-fired burners with Re-Burn technology
- Treatment program2 piles of 1,500 m³ and 2,000 m³ (6,720 tonnes in total)
- Contaminated vapour managementRe-Burn; activated carbon filter on the chimney
- Process controlSoil temperature at cold points, soil pressure, combustion gases and chimney emissions

Results
All samples below targets: C10–C40 <2,250 mg/kg, BTEX <1.6 mg/kg, PAH <500 mg/kg
65 days per piletreatment time
Soil remediated for a future commercial area

Reference sheet
Technical summary of this project, sent on request.